TULE WIND — Project Summary

Queue ID
CAISO-32
Capacity
193.8 MW
Technology
Wind
Status
active
Location
San Diego, CA
Region
CAISO
Developer
IA Status
IA Executed

TULE WIND

BetaActiveWindCAISOLBNL + Live

193.8 MW generation in San Diego, CA · In queue since May 2004 · Proposed COD October 2030

193.8 MW

Capacity

1

Components

Wind

21y 10m

In Queue

IA Executed

IA Status

Signed Mar 2011

Interconnection Timeline

Queue → IA

6y 10m

IA → COD

19y 7m

Total Duration

6y 10m

Construction75%
Queue EntryMay 24, 2004

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementMar 23, 2011

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2030-10-31

Project Details

State

CA

County

San Diego

Region

CAISO

Developer

Utility

SDGE

Entity

CAISO

Point of Interconnection

Boulevard East Substation 138 kV

Data Source

LBNL + Live