ALTA VISTA SUNTOWER GENERATING STATION
BetaActiveSolarBatteryCAISOLBNL + Live
132 MW hybrid in Los Angeles, CA · In queue since January 2008 · Proposed COD December 2027
132 MW
Capacity
2
Components
Solar + Battery
18y 2m
In Queue
IA Executed
IA Status
Signed Jun 2011
Interconnection Timeline
Queue → IA
3y 5m
IA → COD
16y 6m
Total Duration
3y 5m
Construction75%
Queue EntryJan 18, 2008
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJun 30, 2011
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-12-11
Technology
Solar66 MW · 50%
Battery66 MW · 50%
Project Details
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Neenach-Bailey 66kV line
Data Source
LBNL + Live