AMERICAN KINGS SOLAR — Project Summary

Queue ID
CAISO-272
Capacity
196.8 MW
Technology
Solar+Battery
Status
active
Location
Kings, CA
Region
CAISO
Developer
IA Status
IA Executed

AMERICAN KINGS SOLAR

BetaActiveSolarBatteryCAISOLBNL + Live

196.8 MW hybrid in Kings, CA · In queue since November 2007 · Proposed COD December 2025

196.8 MW

Capacity

2

Components

Solar + Battery

18y 4m

In Queue

IA Executed

IA Status

Signed Aug 2014

Interconnection Timeline

Queue → IA

6y 9m

IA → COD

11y 4m

Total Duration

6y 9m

Schedule

3 months past proposed COD

Construction75%
Queue EntryNov 1, 2007

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementAug 15, 2014

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-12-30

Technology
Solar123 MW · 63%
Battery73.8 MW · 37%
Project Details

State

CA

County

Kings

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Henrietta 70 kV

Data Source

LBNL + Live

No news available for this project.