MONTEZUMA II
BetaActiveWindBatteryCAISOLBNL + Live
132 MW hybrid in Solano, CA · In queue since May 2007 · Proposed COD January 2012
132 MW
Capacity
2
Components
Wind + Battery
18y 10m
In Queue
IA Executed
IA Status
Signed Dec 2010
Interconnection Timeline
Queue → IA
3y 7m
IA → COD
1y 1m
Total Duration
3y 7m
Schedule
172 months past proposed COD
Construction75%
Queue EntryMay 23, 2007
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementDec 17, 2010
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–36 months
Commercial Operation
Proposed COD: 2012-01-29
Technology
Wind78 MW · 59%
Battery54 MW · 41%
Project Details
State
CA
County
Solano
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Birds Landing 230 kV
Data Source
LBNL + Live