MONTEZUMA II — Project Summary

Queue ID
CAISO-222
Capacity
132 MW
Technology
Wind+Battery
Status
active
Location
Solano, CA
Region
CAISO
Developer
IA Status
IA Executed

MONTEZUMA II

BetaActiveWindBatteryCAISOLBNL + Live

132 MW hybrid in Solano, CA · In queue since May 2007 · Proposed COD January 2012

132 MW

Capacity

2

Components

Wind + Battery

18y 10m

In Queue

IA Executed

IA Status

Signed Dec 2010

Interconnection Timeline

Queue → IA

3y 7m

IA → COD

1y 1m

Total Duration

3y 7m

Schedule

172 months past proposed COD

Construction75%
Queue EntryMay 23, 2007

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementDec 17, 2010

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–36 months

Commercial Operation

Proposed COD: 2012-01-29

Technology
Wind78 MW · 59%
Battery54 MW · 41%
Project Details

State

CA

County

Solano

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Birds Landing 230 kV

Data Source

LBNL + Live