MONTEZUMA (HIGH WINDS III)
BetaActiveWindBatteryCAISOLBNL + Live
76 MW hybrid in Solano, CA · In queue since November 2003 · Proposed COD April 2024
76 MW
Capacity
2
Components
Wind + Battery
22y 4m
In Queue
IA Executed
IA Status
Signed May 2010
Interconnection Timeline
Queue → IA
6y 6m
IA → COD
13y 11m
Total Duration
6y 6m
Schedule
24 months past proposed COD
Construction75%
Queue EntryNov 18, 2003
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementMay 24, 2010
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–36 months
Commercial Operation
Proposed COD: 2024-04-01
Technology
Wind38 MW · 50%
Battery38 MW · 50%
Project Details
State
CA
County
Solano
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Birds Landing 230 kV
Data Source
LBNL + Live