TOWNSHIP EXPANSION
22.6 MW hybrid in Sutter, CA · In queue since October 2022 · Proposed COD June 2024
22.6 MW
Capacity
2
Components
Gas + Battery
3y 5m
In Queue
Feasibility Study
IA Status
COD target: 2024
Total Duration
1y 8m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
State
CA
County
Sutter
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Greenleaf #1 115 kV Tap
Data Source
LBNL
Does PA 233 wrest control from local governments? What experts said
HILLSDALE — Residents concerned about the expansion of large-scale solar, wind and battery energy storage projects gathered March 18 at...
Armour's decision not to allow a Battery Energy Storage System to be appealed at the Ontario Land Tribunal
PowerBank Corporation has provided the Township of Armour with notice that they will be appealing the Township's decision not to allow the...
Energy storage projects surge in Ontario, driven by need for reliability
The start of construction on Canada's largest battery energy storage system south of Ottawa is just one example of Ontario's demand for grid...
Energy storage projects surge in Ontario, driven by need for reliability
The start of construction on Canada's largest battery energy storage system south of Ottawa is just one example of Ontario's demand for grid...
Last updated 2026-03-26