BOULDER BRUSH HYBRID
BetaActiveWindBatteryCAISOLBNL + Live
419.719 MW hybrid in San Diego, CA · In queue since April 2021 · Proposed COD February 2031
419.719 MW
Capacity
2
Components
Wind + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
9y 10m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2031-02-05
Technology
Wind105.8 MW · 25%
Battery313.919 MW · 75%
Project Details
State
CA
County
San Diego
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Suncrest - Ocotillo 500 kV Line
Data Source
LBNL + Live