SOLAR DE MEXICALI
572.26 MW hybrid in Baja California, MX · In queue since April 2021 · Proposed COD March 2030
572.26 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-16
State
MX
County
Baja California
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Imperial Valley Substation 230 kV
Data Source
LBNL + Live
Mexico sanctions former Baja California governor over failed solar contract
A Mexican state court has barred former Baja California Governor Jaime Bonilla from public office as investigations continue into a canceled...
Mexico Experiments With Residential Solar Panels, But They Are Still Insufficient
A wind farm in the state of Baja California, in Northwestern Mexico. This territory depends on fossil fuels for electricity generation,...
Huawei's bet on Mexico's solar revolution
Six years after launching a package of comprehensive solutions for solar energy generation in Mexico, Chinese technology giant Huawei is...
Huawei's bet on Mexico's solar revolution
Six years after launching a package of comprehensive solutions for solar energy generation in Mexico, Chinese technology giant Huawei is...
Last updated 2026-03-26