REMY
BetaActiveSolarBatteryCAISOLBNL + Live
616.47 MW hybrid in Yuma, AZ · In queue since April 2021 · Proposed COD June 2029
616.47 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 2m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-06-30
Technology
Solar308 MW · 50%
Battery308.47 MW · 50%
Project Details
State
AZ
County
Yuma
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Hoodoo Wash Switchyard 500 kV
Data Source
LBNL + Live