SUNBAKED SOLAR
1,023.64 MW hybrid in Inyo, CA · In queue since April 2021 · Proposed COD February 2029
1,023.64 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-02-26
State
CA
County
Inyo
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
Trout Canyon Substation 230 kV
Data Source
LBNL + Live
The World's Largest Tesla Supercharger Station Is Entirely Off-Grid
The company just opened Project Oasis, a massive Supercharger station, in Lost Hills, California. It features 84 stalls that are currently operational and also...
Inside Look at Fresno County Westside Solar Plan to Power 9 Million Homes
A massive solar development project proposed for fallowed farmland on Fresno County's westside would be one of the largest in the world.
Last updated 2026-03-26