KAWICH
BetaActiveSolarBatteryCAISOLBNL + Live
700 MW hybrid in Clark, NV · In queue since April 2021 · Proposed COD July 2029
700 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
IA Executed
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 3m
Construction75%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2029-07-27
Technology
Solar350 MW · 50%
Battery350 MW · 50%
Project Details
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
Innovation-Desert View 230 kV Line
Data Source
LBNL + Live
No news available for this project.