WATER ROCK SOLAR 2
1,033.528 MW hybrid in Nye, NV · In queue since April 2021 · Proposed COD December 2028
1,033.528 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
State
NV
County
Nye
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
Gamebird Substation 230 kV
Data Source
LBNL + Live
Sunset For Nevada Sagebrush?
Sagebrush wildlife habitats are relentlessly battered by public lands grazing depletion. The knee-jerk BLM and Forest Service response to...
Top Geothermal Energy Stocks 2026: Earth’s Power On Tap
The global energy transition is failing a crucial stress test: reliability. Solar panels don't work at night. Wind turbines idle in stagnant...
Solar growth cushions Colorado River hydropower declines
In late May, as the outside temperature approached 100 degrees, Arizona's top water policy officials gathered in an air-conditioned Phoenix...
‘Unprecedented’: Data centers want to triple Nevada’s energy grid capacity
In Las Vegas, not enough water or energy capacity exists to meet data center demands — yet.
Last updated 2026-03-26