DANDELION HYBRID SOLAR
BetaActiveSolarBatteryCAISOLBNL + Live
334.2 MW hybrid in Nye, NV · In queue since April 2021 · Proposed COD December 2027
334.2 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 8m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-26
Technology
Solar223.33 MW · 67%
Battery110.87 MW · 33%
Project Details
State
NV
County
Nye
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
Vista Substation 230 kV
Data Source
LBNL + Live
No news available for this project.