DELAMAR ENERGY STORAGE 2
BetaActiveBatteryCAISOLBNL + Live
256.29 MW storage in Clark, NV · In queue since April 2021 · Proposed COD June 2027
256.29 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 2m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-26
Project Details
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
SCE portion of Eldorado Substation 230 kV
Data Source
LBNL + Live