COMMERCE ENERGY STORAGE 3
256.29 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD February 2031
256.29 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-26
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Laguna Bell Substation 230 kV
Data Source
LBNL + Live
P.E.I. government puts out expression of interest for a battery energy storage system
The announcement was made Monday at a Chamber event . It's looking for 10 to 50 megawatts of energy storage potentially distributed across...
Aypa Power and Six Nations of the Grand River Development Corporation Secure CA$700 Million Financing Close for Ontario Battery Energy Storage Projects
PRNewswire/ - Aypa Power, a Blackstone portfolio company and leading developer, owner, and operator of utility-scale energy storage and...
Aypa Power and Six Nations of the Grand River Development Corporation Secure CA$700 Million Financing Close for Ontario Battery Energy Storage Projects
PRNewswire/ - Aypa Power, a Blackstone portfolio company and leading developer, owner, and operator of utility-scale energy storage and...
Aypa Power and Six Nations of the Grand River Development Corporation Secure CA$700 Million Financing Close for Ontario Battery Energy Storage Projects
PRNewswire/ - Aypa Power, a Blackstone portfolio company and leading developer, owner, and operator of utility-scale energy storage and...
Last updated 2026-03-26