CORAL REEF
405.663 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD April 2032
405.663 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
11 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-04-26
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
El Nido Substation 230 kV
Data Source
LBNL + Live
Indonesia's "Amazon of the Seas" threatened by EV nickel rush
Nickel mining has been expanding in Indonesia's Raja Ampat, fuelled by the world's demand for EV batteries – but Indigenous communities are campaigning to...
Japanese island will reduce power sector emissions to ‘virtually zero’ with renewable microgrid
A tiny, coral reef-surrounded island in southern Japan will be able to use renewable energy as its main source of power, thanks to a microgrid with battery...
Japanese island will reduce power sector emissions to ‘virtually zero’ with renewable microgrid
A tiny, coral reef-surrounded island in southern Japan will be able to use renewable energy as its main source of power, thanks to a microgrid with battery...
Japanese island will reduce power sector emissions to ‘virtually zero’ with renewable microgrid
A tiny, coral reef-surrounded island in southern Japan will be able to use renewable energy as its main source of power, thanks to a microgrid with battery...
Last updated 2026-03-26