GABRIEL STORAGE
405.751 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD May 2033
405.751 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2033
Total Duration
12y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2033-05-15
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Rio Hondo Substation 230 kV
Data Source
LBNL + Live
Blackstone’s Aypa Power secures California BESS agreement, Texas tax exemption
Blackstone portfolio company Aypa Power has secured an energy storage service agreement (ESSA) with community electricity provider Ava Community Energy (Ava).
Blackstone’s Aypa Power secures California BESS agreement, Texas tax exemption
Blackstone portfolio company Aypa Power has secured an energy storage service agreement (ESSA) with community electricity provider Ava Community Energy (Ava).
Last updated 2026-03-26