FLEETWOOD
BetaActiveBatteryCAISOLBNL + Live
405.515 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD April 2032
405.515 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2032
Interconnection Timeline
Total Duration
11 years
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2032-04-28
Project Details
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Litehipe Substation 230 kV
Data Source
LBNL + Live