CADY SOLAR
625.92 MW hybrid in San Bernardino, CA · In queue since April 2021 · Proposed COD February 2031
625.92 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-26
State
CA
County
San Bernardino
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Pisgah Substation 230 kV
Data Source
LBNL + Live
Life just got a little sweeter for Duke Energy Renewables
Duke Energy Renewables has acquired a 50-percent stake in Mesquite Creek Wind, a 211-megawatt (MW) wind power project near Lamesa, Texas.
Life just got a little sweeter for Duke Energy Renewables
Duke Energy Renewables has acquired a 50-percent stake in Mesquite Creek Wind, a 211-megawatt (MW) wind power project near Lamesa, Texas.
Life just got a little sweeter for Duke Energy Renewables
Duke Energy Renewables has acquired a 50-percent stake in Mesquite Creek Wind, a 211-megawatt (MW) wind power project near Lamesa, Texas.
Life just got a little sweeter for Duke Energy Renewables
Duke Energy Renewables has acquired a 50-percent stake in Mesquite Creek Wind, a 211-megawatt (MW) wind power project near Lamesa, Texas.
Last updated 2026-03-26