SIENNA SOLAR 2 — Project Summary

Queue ID
CAISO-2097
Capacity
112 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
IA Status
In Progress (unknown study)

SIENNA SOLAR 2

BetaActiveSolarBatteryCAISOLBNL + Live

112 MW hybrid in San Bernardino, CA · In queue since April 2021 · Proposed COD March 2029

112 MW

Capacity

2

Components

Solar + Battery

4y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

7y 11m

In Study38%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-26

Technology
Solar56 MW · 50%
Battery56 MW · 50%
Project Details

State

CA

County

San Bernardino

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Calcite Substation 230 kV

Data Source

LBNL + Live