SOLSKEN — Project Summary

Queue ID
CAISO-2085
Capacity
809.42 MW
Technology
Solar+Battery
Status
active
Location
Tulare, CA
Region
CAISO
Developer
IA Status
System Impact Study

SOLSKEN

BetaActiveSolarBatteryCAISOLBNL + Live

809.42 MW hybrid in Tulare, CA · In queue since April 2021 · Proposed COD February 2033

809.42 MW

Capacity

2

Components

Solar + Battery

4y 11m

In Queue

System Impact Study

IA Status

COD target: 2033

Interconnection Timeline

Total Duration

11y 10m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2033-02-26

Technology
Solar464.42 MW · 57%
Battery345 MW · 43%
Project Details

State

CA

County

Tulare

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Springville Substation 230 kV

Data Source

LBNL + Live