DRIFTER ENERGY STORAGE — Project Summary

Queue ID
CAISO-2066
Capacity
504.8 MW
Technology
Battery
Status
active
Location
Ventura, CA
Region
CAISO
Developer
IA Status
System Impact Study

DRIFTER ENERGY STORAGE

BetaActiveBatteryCAISOLBNL + Live

504.8 MW storage in Ventura, CA · In queue since April 2021 · Proposed COD March 2033

504.8 MW

Capacity

1

Components

Battery

4y 11m

In Queue

System Impact Study

IA Status

COD target: 2033

Interconnection Timeline

Total Duration

11y 11m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2033-03-26

Project Details

State

CA

County

Ventura

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Moorpark Substation 230 kV