DORIAN STORAGE — Project Summary

Queue ID
CAISO-2062
Capacity
213.5926 MW
Technology
Battery
Status
active
Location
Los Angeles, CA
Region
CAISO
Developer
IA Status
System Impact Study

DORIAN STORAGE

BetaActiveBatteryCAISOLBNL + Live

213.593 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD August 2034

213.593 MW

Capacity

1

Components

Battery

4y 11m

In Queue

System Impact Study

IA Status

COD target: 2034

Interconnection Timeline

Total Duration

13y 4m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2034-08-26

Project Details

State

CA

County

Los Angeles

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Antelope Substation 230 kV