SAGEBRUSH ENERGY STORAGE
528 MW storage in Kern, CA · In queue since April 2021 · Proposed COD February 2033
528 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2033
Total Duration
11y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2033-02-26
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Vincent Substation 230 kV
Data Source
LBNL + Live
Sunset For Nevada Sagebrush?
Sagebrush wildlife habitats are relentlessly battered by public lands grazing depletion. The knee-jerk BLM and Forest Service response to...
Energy developer Fermi in concurrent IPO on LSE and NASDAQ
US energy developer Fermi has become the first company to complete a concurrent dual listing on both Nasdaq and the London Stock Exchange.
Energy developer Fermi in concurrent IPO on LSE and NASDAQ
US energy developer Fermi has become the first company to complete a concurrent dual listing on both Nasdaq and the London Stock Exchange.
Solar and wind energy’s impact on agriculture
The proposed Lava Ridge Wind Project is a commercial-scale wind energy facility and would consist of up to 400 wind turbines and associated...
Last updated 2026-03-26