J90 ENERGY STORAGE
BetaActiveBatteryCAISOLBNL + Live
261 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD June 2033
261 MW
Capacity
1
Components
Battery
4y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2033
Interconnection Timeline
Total Duration
12y 2m
In Study38%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2033-06-01
Project Details
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Antelope Substation 230 kV
Data Source
LBNL + Live
No news available for this project.