BOUSE SOLAR AND STORAGE PLANT
BetaActiveSolarBatteryCAISOLBNL + Live
2,020.78 MW hybrid in La Paz, AZ · In queue since April 2021 · Proposed COD December 2033
2,020.78 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2033
Interconnection Timeline
Total Duration
12y 8m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2033-12-26
Technology
Solar1,009.9 MW · 50%
Battery1,010.88 MW · 50%
Project Details
State
AZ
County
La Paz
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Colorado River - Palo Verde 500kV
Data Source
LBNL + Live
No news available for this project.