INVICTUS
BetaActiveSolarBatteryCAISOLBNL + Live
860.384 MW hybrid in Riverside, CA · In queue since April 2021 · Proposed COD November 2029
860.384 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 7m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-11-26
Technology
Solar430.192 MW · 50%
Battery430.192 MW · 50%
Project Details
State
CA
County
Riverside
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Colorado River 230 kV
Data Source
LBNL + Live
No news available for this project.