INVICTUS — Project Summary

Queue ID
CAISO-2045
Capacity
860.384 MW
Technology
Solar+Battery
Status
active
Location
Riverside, CA
Region
CAISO
Developer
IA Status
System Impact Study

INVICTUS

BetaActiveSolarBatteryCAISOLBNL + Live

860.384 MW hybrid in Riverside, CA · In queue since April 2021 · Proposed COD November 2029

860.384 MW

Capacity

2

Components

Solar + Battery

4y 11m

In Queue

System Impact Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

8y 7m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-11-26

Technology
Solar430.192 MW · 50%
Battery430.192 MW · 50%
Project Details

State

CA

County

Riverside

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Colorado River 230 kV

Data Source

LBNL + Live