HARQUAHALA SUNRISE 2
BetaActiveSolarBatteryCAISOLBNL + Live
330.18 MW hybrid in Maricopa, AZ · In queue since April 2021 · Proposed COD September 2026
330.18 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 5m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-01
Technology
Solar169.2 MW · 51%
Battery160.98 MW · 49%
Project Details
State
AZ
County
Maricopa
Region
CAISO
Developer
—
Utility
DCRT
Entity
CAISO
Point of Interconnection
Delaney Substation 500 kV
Data Source
LBNL + Live
No news available for this project.