RANEGRAS PVS
BetaActiveSolarBatteryCAISOLBNL + Live
1,437.62 MW hybrid in La Paz, AZ · In queue since April 2021 · Proposed COD July 2029
1,437.62 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 3m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-26
Technology
Solar718.81 MW · 50%
Battery718.81 MW · 50%
Project Details
State
AZ
County
La Paz
Region
CAISO
Developer
—
Utility
DCRT
Entity
CAISO
Point of Interconnection
Colorado River-Delaney 500 kV line
Data Source
LBNL + Live
News & Articles (1)Beta