JOVE SOLAR
4,132.6 MW hybrid in La Paz, AZ · In queue since April 2021 · Proposed COD January 2030
4,132.6 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-01-26
State
AZ
County
La Paz
Region
CAISO
Developer
—
Utility
DCRT
Entity
CAISO
Point of Interconnection
Cielo Azul Substation 500 kV
Data Source
LBNL + Live
BLM releases final environmental analysis for Jove Solar Project
PHOENIX — The Bureau of Land Management today released the final Environmental Impact Statement for the Jove Solar Project,...
BLM to hold public meetings mid-January for proposed 600 MW Jove Solar facility
The Bureau of Land Management will hold two public meetings for public comments on the Jove Solar Project, a proposed 600 MWac utility-scale solar project.
BLM to hold public meetings mid-January for proposed 600 MW Jove Solar facility
The large solar facility is part of a 1 GW portfolio of projects proposed for construction on BLM land in Arizona.
BLM to hold public meetings mid-January for proposed 600 MW Jove Solar facility
The large solar facility is part of a 1 GW portfolio of projects proposed for construction on BLM land in Arizona.
Last updated 2026-03-26