SOCORRO PEAK SOLAR
BetaActiveSolarBatteryCAISOLBNL + Live
755.791 MW hybrid in La Paz, AZ · In queue since April 2021 · Proposed COD March 2029
755.791 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7y 11m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-03-26
Technology
Solar379.751 MW · 50%
Battery376.04 MW · 50%
Project Details
State
AZ
County
La Paz
Region
CAISO
Developer
—
Utility
DCRT
Entity
CAISO
Point of Interconnection
Cielo Azul Substation 500 kV
Data Source
LBNL + Live
No news available for this project.