BUTTONBUSH SOLAR 2
BetaActiveSolarBatteryCAISOLBNL + Live
716.4 MW hybrid in Kern, CA · In queue since April 2021 · Proposed COD March 2032
716.4 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2032
Interconnection Timeline
Total Duration
10y 11m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2032-03-17
Technology
Solar358.2 MW · 50%
Battery358.2 MW · 50%
Project Details
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Midway 500 kV
Data Source
LBNL + Live