PEACEFUL HOLLOW BESS
BetaActiveBatteryCAISOLBNL + Live
100 MW storage in Fresno, CA · In queue since April 2021 · Proposed COD June 2028
100 MW
Capacity
1
Components
Battery
4y 11m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 2m
Construction75%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-06-18
Project Details
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Tranquility 230kV
Data Source
LBNL + Live
No news available for this project.