PLUM — Project Summary

Queue ID
CAISO-1968
Capacity
1560 MW
Technology
Solar+Battery
Status
active
Location
Kings, CA
Region
CAISO
Developer
IA Status
System Impact Study

PLUM

BetaActiveSolarBatteryCAISOLBNL + Live

1,560 MW hybrid in Kings, CA · In queue since April 2021 · Proposed COD March 2031

1,560 MW

Capacity

2

Components

Solar + Battery

4y 11m

In Queue

System Impact Study

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

9y 11m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-03-19

Technology
Solar1,040 MW · 67%
Battery520 MW · 33%
Project Details

State

CA

County

Kings

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Gates 230 kV

Data Source

LBNL + Live