CORNUCOPIA HYBRID — Project Summary

Queue ID
CAISO-1959
Capacity
604.629 MW
Technology
Solar+Battery
Status
active
Location
Fresno, CA
Region
CAISO
Developer
IA Status
IA Executed

CORNUCOPIA HYBRID

BetaActiveSolarBatteryCAISOLBNL + Live

604.629 MW hybrid in Fresno, CA · In queue since April 2021 · Proposed COD November 2030

604.629 MW

Capacity

2

Components

Solar + Battery

4y 11m

In Queue

IA Executed

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

9y 7m

Construction75%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2030-11-16

Technology
Solar303.678 MW · 50%
Battery300.951 MW · 50%
Project Details

State

CA

County

Fresno

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Gates-Templeton 230 kV Line

Data Source

LBNL + Live