HUASO HYBRID — Project Summary

Queue ID
CAISO-1954
Capacity
203.93 MW
Technology
Solar+Battery
Status
active
Location
Fresno, CA
Region
CAISO
Developer
IA Status
System Impact Study

HUASO HYBRID

BetaActiveSolarBatteryCAISOLBNL + Live

203.93 MW hybrid in Fresno, CA · In queue since April 2021 · Proposed COD December 2026

203.93 MW

Capacity

2

Components

Solar + Battery

4y 11m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 8m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-03

Technology
Solar102.1 MW · 50%
Battery101.83 MW · 50%
Project Details

State

CA

County

Fresno

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Gates 230 kV

Data Source

LBNL + Live

No news available for this project.