HUASO HYBRID
BetaActiveSolarBatteryCAISOLBNL + Live
203.93 MW hybrid in Fresno, CA · In queue since April 2021 · Proposed COD December 2026
203.93 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 8m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-03
Technology
Solar102.1 MW · 50%
Battery101.83 MW · 50%
Project Details
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Gates 230 kV
Data Source
LBNL + Live
No news available for this project.