FLORES STORAGE
151.742 MW storage in Madera, CA · In queue since April 2021 · Proposed COD February 2031
151.742 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-18
State
CA
County
Madera
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Gregg 230 kV
Data Source
LBNL + Live
Wheatland panel rejects plans for Highway 50 battery storage plant; project goes to Town Board
A Wheatland town panel roundly rejected a proposed battery energy storage facility planned at 392nd Avenue and Highway 50 after nearly four...
Microgrid Boosts San Pasqual Band’s Energy Sovereignty and Security
The Tribe commissioned a hybrid solar-storage-liquid propane microgrid system to boost energy reliability and resilience on the Reservation.
Last updated 2026-03-26