DARDEN
BetaActiveSolarBatteryCAISOLBNL + Live
2,364.768 MW hybrid in Fresno, CA · In queue since April 2021 · Proposed COD July 2027
2,364.768 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 3m
Construction75%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-07-19
Technology
Solar1,182.384 MW · 50%
Battery1,182.384 MW · 50%
Project Details
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Manning-Midway 500kV Line
Data Source
LBNL + Live