LOTUS SOLAR 2
406.4 MW hybrid in Madera, CA · In queue since April 2021 · Proposed COD November 2030
406.4 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
9y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-11-17
State
CA
County
Madera
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Borden 230 kV
Data Source
LBNL + Live
Tesla Inc. – Mid-2025 Comprehensive Company Report (June 28th, 2025)
Tesla posted Q1 2025 net income of $0.4 billion, down 71% year-on-year, with deliveries falling to about 336700 vehicles amid Model Y...
Vistra to Acquire 2.6 GW Gas Fleet for $1.9B, Citing Surging U.S. Power Demand
Vistra Corp. has agreed to acquire seven natural gas power plants totaling 2557 MW from Lotus Infrastructure Partners for $1.9 billion,...
Vistra to Acquire 2.6 GW Gas Fleet for $1.9B, Citing Surging U.S. Power Demand
Vistra Corp. has agreed to acquire seven natural gas power plants totaling 2557 MW from Lotus Infrastructure Partners for $1.9 billion,...
Vistra to Acquire 2.6 GW Gas Fleet for $1.9B, Citing Surging U.S. Power Demand
Vistra Corp. has agreed to acquire seven natural gas power plants totaling 2557 MW from Lotus Infrastructure Partners for $1.9 billion,...
Last updated 2026-03-26