APACHE STORAGE
203.699 MW storage in Fresno, CA · In queue since April 2021 · Proposed COD May 2029
203.699 MW
Capacity
1
Components
Battery
4y 11m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2029-05-21
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Sanger 115 kV
Data Source
LBNL + Live
SRP wants to convert this coal unit to natural gas. What it means for your energy mix
Salt River Project hopes to convert a coal-fired unit to natural gas at Springerville Generating Station, one of Arizona's last remaining...
SRP wants to convert this coal unit to natural gas. What it means for your energy mix
Salt River Project hopes to convert a coal-fired unit to natural gas at Springerville Generating Station, one of Arizona's last remaining...
SRP wants to convert this coal unit to natural gas. What it means for your energy mix
Salt River Project hopes to convert a coal-fired unit to natural gas at Springerville Generating Station, one of Arizona's last remaining...
SRP wants to convert this coal unit to natural gas. What it means for your energy mix
Salt River Project hopes to convert a coal-fired unit to natural gas at Springerville Generating Station, one of Arizona's last remaining...
Last updated 2026-03-26