EL REY POWER BANK
BetaActiveBatteryCAISOLBNL + Live
124.3 MW storage in Monterey, CA · In queue since April 2021 · Proposed COD January 2029
124.3 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7y 9m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-02
Project Details
State
CA
County
Monterey
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Coburn-Basic Energy 60 kV Line
Data Source
LBNL + Live
No news available for this project.