ZORIN STORAGE — Project Summary

Queue ID
CAISO-1911
Capacity
252 MW
Technology
Battery
Status
active
Location
Alameda, CA
Region
CAISO
Developer
IA Status
System Impact Study

ZORIN STORAGE

BetaActiveBatteryCAISOLBNL + Live

252 MW storage in Alameda, CA · In queue since April 2021 · Proposed COD February 2034

252 MW

Capacity

1

Components

Battery

4y 11m

In Queue

System Impact Study

IA Status

COD target: 2034

Interconnection Timeline

Total Duration

12y 10m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2034-02-19

Project Details

State

CA

County

Alameda

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Newark 230 kV

Data Source

LBNL + Live

No news available for this project.