GOLDEN FLATS
365.12 MW storage in Stanislaus, CA · In queue since April 2021 · Proposed COD September 2031
365.12 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
10y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-09-01
State
CA
County
Stanislaus
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Westly-Quinto 230 kV
Data Source
LBNL + Live
Evacuation orders lifted for Parkfield Solar Plant fire
Update 8:20 p.m.: Evacuation orders were lifted. Public safety officials continue to monitor the fire and a Tesla Field Service Response...
Georgia Power kicks off construction on 765 MW of BESS | Projects Weekly
Georgia Power has commenced construction on 765 MW of new battery energy storage systems (BESS) strategically located across Georgia in Bibb, Lowndes, Floyd...
Georgia Power kicks off construction on 765 MW of BESS | Projects Weekly
Georgia Power has commenced construction on 765 MW of new battery energy storage systems (BESS) strategically located across Georgia in Bibb, Lowndes, Floyd...
Georgia Power kicks off construction on 765 MW of BESS | Projects Weekly
Georgia Power has commenced construction on 765 MW of new battery energy storage systems (BESS) strategically located across Georgia in Bibb, Lowndes, Floyd...
Last updated 2026-03-26