HOLMAN — Project Summary

Queue ID
CAISO-1889
Capacity
2281.985 MW
Technology
Wind+Battery
Status
active
Location
Monterey, CA
Region
CAISO
Developer
IA Status
System Impact Study

HOLMAN

BetaActiveWindBatteryCAISOLBNL + Live

2,281.985 MW hybrid in Monterey, CA · In queue since April 2021 · Proposed COD February 2034

2,281.985 MW

Capacity

2

Components

Wind + Battery

4y 11m

In Queue

System Impact Study

IA Status

COD target: 2034

Interconnection Timeline

Total Duration

12y 10m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2034-02-17

Technology
Wind1,525.172 MW · 67%
Battery756.813 MW · 33%
Project Details

State

CA

County

Monterey

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Moss Landing 500 kV

Data Source

LBNL + Live