WILDHORSE ENERGY CENTER
BetaActiveBatteryCAISOLBNL + Live
121.55 MW storage in Sonoma, CA · In queue since April 2021 · Proposed COD May 2030
121.55 MW
Capacity
1
Components
Battery
4y 11m
In Queue
System Impact Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
9y 1m
Impact Study25%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-05-04
Project Details
State
CA
County
Sonoma
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Fulton 230 kV
Data Source
LBNL + Live
No news available for this project.