SCAFELL STORAGE
BetaActiveBatteryCAISOLBNL + Live
52 MW storage in San Diego, CA · In queue since April 2020 · Proposed COD June 2029
52 MW
Capacity
1
Components
Battery
5y 11m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
9y 2m
Impact Study25%
Queue EntryApr 15, 2020
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-06-30
Project Details
State
CA
County
San Diego
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Creelman Substation 69 kV
Data Source
LBNL + Live