CAPTIVA ENERGY STORAGE
BetaActiveBatteryCAISOLBNL + Live
256.875 MW storage in Orange, CA · In queue since April 2020 · Proposed COD June 2028
256.875 MW
Capacity
1
Components
Battery
5y 11m
In Queue
IA Executed
IA Status
Signed May 2022
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
6y 1m
Total Duration
2y 1m
Construction75%
Queue EntryApr 15, 2020
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementMay 18, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-06-01
Project Details
State
CA
County
Orange
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Trabuco - Capistrano 138 kV Line
Data Source
LBNL + Live