CAPTIVA ENERGY STORAGE — Project Summary

Queue ID
CAISO-1806
Capacity
256.875 MW
Technology
Battery
Status
active
Location
Orange, CA
Region
CAISO
Developer
IA Status
IA Executed

CAPTIVA ENERGY STORAGE

BetaActiveBatteryCAISOLBNL + Live

256.875 MW storage in Orange, CA · In queue since April 2020 · Proposed COD June 2028

256.875 MW

Capacity

1

Components

Battery

5y 11m

In Queue

IA Executed

IA Status

Signed May 2022

Interconnection Timeline

Queue → IA

2y 1m

IA → COD

6y 1m

Total Duration

2y 1m

Construction75%
Queue EntryApr 15, 2020

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementMay 18, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

CA

County

Orange

Region

CAISO

Developer

Utility

SDGE

Entity

CAISO

Point of Interconnection

Trabuco - Capistrano 138 kV Line

Data Source

LBNL + Live

No news available for this project.