PURPLE SAGE ENERGY CENTER
BetaActiveSolarBatteryCAISOLBNL + Live
817.44 MW hybrid in Clark, NV · In queue since April 2020 · Proposed COD May 2028
817.44 MW
Capacity
2
Components
Solar + Battery
5y 11m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 1m
Construction75%
Queue EntryApr 15, 2020
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2028-05-01
Technology
Solar409.2 MW · 50%
Battery408.24 MW · 50%
Project Details
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
Trout Canyon Substation 230 kV
Data Source
LBNL + Live
No news available for this project.