ROUGH HAT 2
407.6 MW hybrid in Clark, NV · In queue since April 2020 · Proposed COD December 2027
407.6 MW
Capacity
2
Components
Solar + Battery
5y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-01
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
Trout Canyon Substation 230 kV
Data Source
LBNL + Live
Trump Administration Cancels a Large Nevada Solar Plant
The Trump administration canceled the proposed Esmeralda 7 Solar Project in Nevada that would have been among the world's largest solar...
BLM seeks public input on 200 MW solar project in Nevada
The Dodge Flat II solar project will take approximately two years to complete, employing as many as 350 area workers at peak construction.
BLM seeks public input on 200 MW solar project in Nevada
The Dodge Flat II solar project will take approximately two years to complete, employing as many as 350 area workers at peak construction.
As solar farms sprout up in Southern Nevada, concern for desert tortoises grows
As solar energy farms continue to pop up across the Mojave Desert, some residents are being squeezed out of their homes: the threatened...
Last updated 2026-03-26