DELAMAR ENERGY STORAGE
BetaActiveBatteryCAISOLBNL + Live
256.29 MW storage in Clark, NV · In queue since April 2020 · Proposed COD June 2027
256.29 MW
Capacity
1
Components
Battery
5y 11m
In Queue
IA Executed
IA Status
Signed Oct 2022
Interconnection Timeline
Queue → IA
2y 6m
IA → COD
4y 8m
Total Duration
2y 6m
Construction75%
Queue EntryApr 15, 2020
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementOct 19, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Eldorado Substation 230kV
Data Source
LBNL + Live
No news available for this project.